Short Term Releases

Alt. Routes & Juror Info

TX DOT

Real Time Traffic Map

Smith & Travis Construction

Chronicle Traffic Page

Ordinances

Current Accidents

Downtown Maps

Frequently Asked Questions

Parking

Downtown Links

Pedestrian Regulations

Stop Trashing Houston

2005 Overview

Northside Sidewalks


Below is the most up to date information we have on the progress of Smith and Travis Street Construction as provided to us by: Connie Roebuck Community Outreach Representative
Downtown / Midtown Transit Streets Project 713.739.4896
croebuck@ridemetro.org

This update is to give you an update on Travis and Smith Streets' construction as of 4-8-05

Travis Update:

Tomorrow, on Friday, July 1, the contractor for Travis St. construction will move traffic to travel on the new west-lane  pavement three more blocks south – which means either at Texas or  just north of Texas, through Commerce, traffic will use the east lanes.  West-side excavation will begin in those blocks either Friday or Monday.  (It looks like Texas Sterling Construction will not be working on  Travis the 4th of July holiday weekend, Sat.-Mon.)

Previously:

The contractor had to adjust his short-term schedule as some issues were resolved, but the overall timeline is still on target. Now that the construction activity has moved into the northern ends, you will see more parking restrictions not only on Travis but  also on the cross streets. While Texas Sterling is waiting as long  as possible before taking any parking away, please be ready to adjust  for it. Some areas on the cross streets, particularly toward Milam  and toward Main will have to share zones. The best option we can see is that some of that area is loading & unloading by day (usually 9-4)  and valet by night (usually 6PM-3AM). Texas Ave. will be the exception

– but that means LOTS of sharing there. And a reminder about some  METRO commuter buses returning to Smith from a detour on Milam: Monday, April 11, the following buses will return to their regular route onto  Smith. If you know of anyone who uses one of these Park & Ride buses,  please pass the word in case they have not seen the notices on their  buses.

- 214 Northwest Station and 216 West Little York/Pinemont INBOUND
- 261West Loop, 262 Westwood, and 265 West Bellfort OUTBOUND

There are still many different parts to the work to be done, especially  behind the curb. As a pedestrian, please watch out for areas of unfinished  work.

Smith Update:

For those of you who use that short piece of Brazos at the south end of downtown, METRO has asked that we coordinate our efforts to return that portion to one-way on April 16. And a reminder about some METRO commuter buses returning to Smith from a detour on Milam: Monday, April 11, the following buses will return to their regular route onto Smith.

If you know of anyone who uses one of these Park & Ride buses, please  pass the word in case they have not seen the notices on their buses.

- 214 Northwest Station and 216 West Little York/Pinemont INBOUND
- 261West Loop, 262 Westwood, and 265 West Bellfort OUTBOUND

There are still many different parts to the work to be done, especially  behind the curb. As a pedestrian, please watch out for areas of unfinished  work.

3-29-05

The anticipated expansion of the project up to Commerce  will not happen tomorrow (Wed., March 30) as expected. We’re still  waiting for the approval of the permit, and will possibly get that  documented approval Friday afternoon. We will see if that permit does indeed get issued, and if the contractor can still get the crew on Monday. - The sanitary work is presently moving from Prairie south;  that work should continue between Texas and Prairie through the middle  of next week. Then, the work continues south to Capitol.

- Tomorrow, the waterline work will begin in the Capitol to Texas  block; that work is expected to take 7 days and then move to the Texas  to Prairie block.
- And just to give you some hope for the Walker intersection
– it’s expected that concrete will be poured on the east side of Travis  in the Walker intersection by the middle of April. That very dense  underground in the Walker intersection has taken a lot of time and  attention by several contractors. While it will not be completed on  the west side for several more weeks, it should be a calmer site after  mid-April.

Please be careful when traveling or walking in the area. We still  have several months to go.

Connie Roebuck
Community Outreach Representative
Downtown / Midtown Transit Streets Project
713.739.4896
croebuck@ridemetro.org



The Houston  Downtown Management District would like to thank you for visiting DowntownStreets.com.  We always welcome your comments and feedback. This site is produced with information by and in conjunction with the following: Houston Downtown  Management District, Metro, TX DOT, Harris County, City of Houston,  Houston Transtar and Central Houston.
Page Last Updated: November 3, 2005
Click  Here to Email Us