This page provides information about the
Downtown District's Northside Sidewalk Project
in the area between Buffalo Bayou and I-10.
The project is being designed based on the Master Plan.
The Master Plan
can be downloaded by clicking here.
This is a large file (740k) and will take several minutes to download
on a dial-up connection.
It is a pdf file and will require Adobe Acrobat Reader to view.
Go
here to download the free Reader.
When reviewing the Master Plan please remember that the improvements
suggested along I-10 will not be included in the design due to near-term
changes to that area by other agencies.
Plan to Attend
Stakeholder Meeting
July 18, 6:00 PM
Last Concert Cafe
1403 Nance Street
Milestones for the project are:
-
7/18/05 Stakeholder Meeting at 6:00 PM at the
Last Concert Cafe, 1403 Nance Street
-
7/18/05 Design to be 50% complete.
-
8/12/05 Design to be 70% complete and submitted
to City for review
-
9/16/05 Design to be 90% complete
-
9/19-21/05Stakeholder meeting
-
9/20-22/05 Modify design after stakeholder meeting
if necessary and submit to City for 90% review.
-
10/19/05 Design and contract documents complete
and submitted to City for Signatures.
-
11/14/05 Obtained approvals from City and prepare
prints for bidding.
-
11/17/05 Advertise for Bids
-
1/12/05 HDMD Board approve award of contract
-
1/30/06 Contractor's insurance and other paper
work submitted and construction begins.

- For answers to questions or to submit ideas and suggestions contact
Tom Davis at 713-650-3022 or tom@downtowndistrict.org.